Use the Activity Dashboard

As soon as you (or other project members) create activities for a project, an Activity Dashboard becomes available. This dashboard can show data for all activities in the project or for a single activity at a time.

You can select a different activity to review in the list at the upper right.

Use this dashboard to review these default widgets:

You can input a number for the Target Working Rate. This would match up to the actual rate when you type in this number rather than deriving the target working rate from two dates. This, in turn, calculates a date in the future that is calendar days.

Because the actual working rate is calculated using only the days when earth was moved that matched the subtype of the activity, non-working/weekend days and days when earth was not moved due to working on another area of the site are not used. 

Recommendation: Enter the Start Day and a target working rate, which will thus compare a proper target vs actual working rate.

When you do this from the progress bar to the map, the total remaining value on the Activity Dashboard is consistent with the Total Volume value in the Remaining tab, but the Total Completed value (on the Activity Dashboard) may not be in sync with the Total Volume on the Completed tab (Cut Completed = (Estimated Cut - Cut Remaining)).

Tip:  Draw a profile through the activity area to see the progress of work based on different surveyed surfaces versus the design

The Activity Dashboard widgets act as filters using the activity's specific parameters. When you click the progress bar to open the Map view for an activity you can set additional filters, run queries, create profile views, and run reports. 

See work remaining for an entire activity

By default, the Work Remaining widget on the Activity page shows the last seven days of work. If you click the Work Remaining widget for an activity, you can see the work remaining for the entire activity. While in this view, you can select a different activity to see the work remaining “burndown” for it. 

The Work Remaining widget appears for all cut, fill, and cut/fill activities. Within progress volumes, the entire history of activity progress is shown, along with the start and end dates, design name, total estimated quantity, target and actual working rates, and working days. This view allows you to view trends over the activity’s timeline. The activity shown can be easily changed using a drop-down list. The table view provides a numerical view with a CSV file download option, while the map gives a current or historic view of the cut/fill map for the work remaining. 

Next topic: Edit Activities